
KBH Campus Expansion Construction Update for the Week of 1/23/2023.
*Please note that what was once called Health Care, will now be known as the Martin Jahn Nursing Pavilion
Martin Jahn Nursing Pavilion
Garden Level
• Aluminum entrance doors are in and waiting for the glass inserts to be installed.
• Work on the Porte Cochere plaster ceiling and columns continues and will take approx. two weeks.
• The tile floor is installed in the main entry and is being grouted today.
• Millwork is continuing throughout, with crown molding being installed in the hallways.
• All resident room floors are in, shower stalls are tiled, and plumbing fixtures in the bathrooms are being installed.
• Hanging of doors in resident rooms is taking place.
• Flooring and cabinetry are being installed in non-common space areas like the clean and soiled utility rooms.
First Level
• Trim work has started.
• Resident room flooring will be completed this week.
• Tiling in the resident rooms, and installing of the vanities and toilets, will be installed over the next week.
• Priming of the walls will start and be completed next week. Then, paint and millwork will begin.
The Gardens
• Footings are in and they continue to pour the foundation walls on top of the footings.
• Pepper has poured 750 yards of the 45,000 required yards to date.
• Underground utilities are being worked on.
• The concrete slab on grade on each side of the building will be poured in a couple of weeks – it will require a lot of concrete as it is 16” thick.