KBH Campus Expansion Construction Update for the Week of 2/27/2023
KBH Campus Expansion Construction Update for the Week of 2/27/2023 Martin Jahn Nursing Pavilion • Last Monday, the electric and mechanical engineers performed a walk-through, and everything is as planned. • Pepper Construction is working on their punch list to...
Why Exercise Is Important for Seniors
As a senior, you’re probably aware of the changes that come with aging — both physical and mental. However, did you know that regular exercise can help combat these changes and even help reduce some of the effects of aging? Imagine having more energy, reducing your...
KBH Campus Expansion Construction Update for the Week of 2/20/2023
KBH Construction Update Martin Jahn Nursing Pavilion Gardens Level Painting and carpeting will be finished by the end of this week The pre-punch list will be developed by Pepper. The mechanical, electrical and plumbing punch list will be developed next week. Crown...
KBH Campus Expansion Construction Update for the Week of 2/13/2023
KBH Construction Update Martin Jahn Nursing Pavilion On February 15th, a group of information technology professionals will be here to start installing the IT infrastructure. This will take approximately 3-4 days. Once installed, they will then schedule the install of...
KBH Campus Expansion Construction Update for the Week of 2/6/2023
KBH Construction Update Martin Jahn Nursing Pavilion Millwork in the Garden level will be finished by the end of this week. Painting will start in the Garden level next week and will take approximately a few weeks. Millwork on the 1st floor will take another two weeks...
KBH Campus Expansion Construction Update for the Week of 1/30/2023
KBH Campus Expansion Construction Update for the Week of 1/30/2023 Martin Jahn Nursing Pavilion Garden Level: Trim and millwork is approximately 90% finished. Work on bathroom fixtures and finishes is taking place. Doors are all installed. Work is taking place on the...
KBH Campus Expansion Construction Update for the Week of 1/23/2023
KBH Campus Expansion Construction Update for the Week of 1/23/2023. *Please note that what was once called Health Care, will now be known as the Martin Jahn Nursing Pavilion Martin Jahn Nursing Pavilion Garden Level • Aluminum entrance doors are in and waiting for the...
KBH Campus Expansion Construction Update for the Week of 1/16/2023
KBH Campus Expansion Construction Update for the Week of 1/16/2023: Some work listed below started last week and will continue this week. Health Care Tiling first floor bathrooms. Tiling soiled clean utility and ancillary spaces on the Garden level. Doors and Hardware...
Fun Winter Activities in Chicago
Looking for activities to do in Chicago during winter? With King-Bruwaert House only being 20 miles from the city, it’s the perfect escape for memorable experiences, especially this time of year. And the great thing is when you’re done having fun, a quick drive back...
KBH Campus Expansion Construction Update for the Week of 1/9/2023
Last Wednesday over 100 of yards of concrete was poured for The Gardens’ walls. The concrete team is busy this week framing up for additional walls which will be poured very soon. The footings and concrete walls for The Gardens should be finished in approximately...